Changes during sprint
We planned 2-week sprint. But after some time situation changed and we have to change to 3-week sprint and we added some US. The problem is with burndown chart. The "points done" line shows the actual stat day by day but "points estimate" line is show for actual size of sprint. It should have same approach - either day by day or based on current state...
I personaly favour the day by day aproach.